An office fit-out in Dubai turns a bare or basic unit into a working space — and whether you're taking a shell in a DIFC tower or a Category A office in a free-zone building, the cost, approvals and timeline follow a predictable pattern. This 2026 guide covers what an office fit-out actually costs per square foot by grade, the difference between Category A and B, the free-zone, DED, Dubai Municipality and Civil Defence approvals you'll need, and a realistic schedule so you can plan your move-in date with confidence.
Key takeaways
- "Category A" is the base building finish; "Category B" is your branded, functional fit-out — most tenant budgets are Cat B.
- Expect roughly AED 60–450 per sq ft in 2026 depending on grade, from a basic functional space to a high-end build.
- Approvals are the critical path: the building or free-zone authority, Dubai Civil Defence (fire) and DEWA all sign off before and after work.
- A straightforward Category B fit-out runs about 4–10 weeks; complex builds with heavy MEP take longer.
Category A vs Category B: what you're actually paying for
The first thing to know is which category you're starting from, because it decides how much is left to build:
- Category A (Cat A) — the landlord's base finish: raised floors, a basic ceiling, standard AC, blank walls and core services. Usable, but generic and empty.
- Category B (Cat B) — your fit-out: partitions and meeting rooms, branding, joinery, flooring, lighting, workstations, AV and any smart systems. This is where nearly all tenant spend goes.
- Shell & core — the rawest start, with only the structure and main services; you build everything, which is more time and cost but total freedom.
Knowing your starting category is what makes any quote comparable. A price per square foot means nothing until you know whether it's building on a finished Cat A or starting from a bare shell.
How much does an office fit-out cost in Dubai in 2026?
Fit-out is usually priced per square foot of the leased area. The 2026 ranges below are for a Category B fit-out on a finished Cat A base; a shell-and-core start adds to every band.
| Fit-out grade | Cost per sq ft | What you get |
|---|---|---|
| Basic / functional | 60–120 | Open plan, standard ceilings, basic partitions |
| Mid-range / corporate | 120–250 | Meeting rooms, glass partitions, branding, upgraded MEP |
| High-end / bespoke | 250–450+ | Premium finishes, joinery, feature areas, full AV & smart |
What pushes the number up: the density of meeting rooms and glass partitions, bespoke joinery, upgraded air-conditioning and electrical loads, and AV or smart-office systems. A trading floor or a client-facing HQ sits at the top; a back-office team sits near the bottom.
Approvals and permits for an office fit-out
This is where Dubai fit-outs are won or lost on schedule. Which authority you answer to depends on where your office sits.
- Your authority — a free-zone office (DMCC, DIFC, JAFZA, Dubai South and others) is approved by that free zone; a mainland office is approved via the Department of Economy and Tourism (DET/DED) and Dubai Municipality.
- Building / landlord NOC — building management approves your drawings and usually holds a refundable fit-out deposit before access is granted.
- Dubai Civil Defence — fire and life-safety approval on the design, and a mandatory inspection before handover. This is the approval that most often gates the move-in date.
- DEWA — for the electrical connection and any load changes.
- Licensed contractor & consultant — approvals are issued against stamped drawings from a registered fit-out contractor and, where required, a consultant.
The fit-out process, step by step
A well-run Category B fit-out follows the same order every time — and running approvals alongside procurement is what keeps it fast:
- Brief & design — headcount, layout, brand and budget become a concept and then a technical drawing set.
- Drawings & approvals — submit to the authority, building management and Civil Defence; secure the NOC and permits.
- Procurement — order long-lead items (glass, joinery, furniture, AV) while approvals run.
- Construction & MEP — partitions, ceilings, flooring, electrical, HVAC and data.
- Testing & Civil Defence inspection — life-safety systems tested and signed off.
- Snagging & handover — defects closed, systems commissioned, keys and documents handed over.
A realistic office fit-out timeline
For a typical Category B office on a finished Cat A base, plan for something like this:
| Stage | Duration |
|---|---|
| Design & drawings | 1–3 weeks |
| Authority & Civil Defence approvals | 1–3 weeks |
| Construction & MEP | 3–8 weeks |
| Testing, inspection & handover | 1–2 weeks |
That's roughly 4–10 weeks end-to-end for a straightforward build, longer for large floors, heavy MEP or a shell-and-core start. As with villas, the approvals — not the construction — are where schedules usually slip, so a partner who runs them in parallel with procurement is worth more than the lowest rate.
How A5renova delivers an office fit-out
We deliver the fit-out as one accountable package: design, authority and Civil Defence approvals, construction, MEP and handover under a single fixed scope, so the move-in date you're promised is one we've planned the approvals around. As part of renovation and fit-out, we translate your headcount and brand into a working space, coordinate interior design from the same table, and can build in smart-office systems — lighting, climate and AV — while the walls are open rather than retrofitting later. Send us the floor, the authority and your target move-in, and we'll give you a real programme, not an optimistic one.
Frequently asked questions
How much does an office fit-out cost in Dubai?+
As a 2026 guide, a basic functional Category B fit-out runs about AED 60–120 per sq ft, a mid-range corporate fit-out AED 120–250, and a high-end bespoke build AED 250–450 and up. The figures assume you're building on a finished Category A base; a shell-and-core start costs more. Meeting-room density, joinery, upgraded MEP and AV or smart systems move the number most.
What is the difference between Category A and Category B fit-out?+
Category A is the landlord's base finish — raised floors, a basic ceiling, standard AC and blank walls. Category B is your fit-out on top: partitions, meeting rooms, branding, joinery, flooring, lighting, workstations and AV. Almost all tenant spend is Category B. A shell-and-core unit has only the structure and main services, so you build everything.
Do I need approvals for an office fit-out in Dubai?+
Yes. You need approval from your authority — the free zone (DMCC, DIFC, JAFZA and others) or, on the mainland, DET/DED with Dubai Municipality — plus a building/landlord NOC, Dubai Civil Defence fire approval with a final inspection, and DEWA for the electrical connection. Approvals are issued against stamped drawings from a licensed fit-out contractor.
How long does an office fit-out take in Dubai?+
A straightforward Category B fit-out on a finished Cat A base typically takes about 4–10 weeks end-to-end: 1–3 weeks for design, 1–3 weeks for approvals, 3–8 weeks for construction and MEP, and 1–2 weeks for testing and handover. Large floors, heavy MEP or a shell-and-core start take longer, and approvals cause most delays.
Is an office fit-out different in a free zone versus mainland?+
The main difference is who approves it. In a free zone (DMCC, DIFC, JAFZA, Dubai South and others) the zone authority handles approvals as a one-stop shop and is often faster. On the mainland you coordinate DET/DED and Dubai Municipality. Either way, Dubai Civil Defence fire approval and a final inspection apply before you can move in.
Who pays for an office fit-out, the landlord or the tenant?+
Usually the tenant pays for the Category B fit-out, while the landlord provides the Category A base. Some leases include a rent-free fit-out period or a contribution toward the works, and building management typically holds a refundable fit-out deposit. It's worth negotiating the fit-out contribution and any free period as part of the lease.